The project is in stage 3. Zero time tolerance has been given for this stage. When checking progress, the project manager noticed that the checkpoint report from the external supplier of the 'e-learning course' is late. As work package progress information is missing, the project manager has decided to raise an exception report.
Is this an appropriate action, and why?
Luann
3 months agoDeonna
2 months agoSherita
2 months agoHuey
2 months agoLoreta
3 months agoSalley
3 months agoClorinda
3 months agoTiera
3 months agoWhitney
4 months agoWeldon
4 months agoRebecka
4 months agoBenton
2 months agoJudy
2 months agoAnglea
2 months agoBrice
2 months agoYolande
3 months agoFrank
3 months agoRosann
4 months agoKindra
4 months agoRoselle
3 months agoJesusa
4 months agoCiara
5 months agoEstrella
4 months agoJoanna
4 months agoMalika
5 months ago