BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Exam PRINCE2-Practitioner Topic 3 Question 58 Discussion

Actual exam question for PRINCE2's PRINCE2-Practitioner exam
Question #: 58
Topic #: 3
[All PRINCE2-Practitioner Questions]

During the 'starting up a project' process, the project manager discusses the standard model for course development with the executive. The project manager then assesses how the Health and Safety Training Project will be delivered, including what products should be delivered in each stage.

Is this an appropriate way to carry out the 'plan the initiation stage' activity, and why?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Karma
6 months ago
I see both sides, but I think option A makes more sense. Planning the initiation stage is crucial for setting the project up for success.
upvoted 0 times
...
Micheal
6 months ago
I disagree with Dorinda. I believe option B is more appropriate. Management controls for the initiation stage need to be defined and approved by the project board.
upvoted 0 times
...
Dorinda
6 months ago
I think option A is the correct answer. The initiation stage work needs to be planned and approved like other project work.
upvoted 0 times
...

Save Cancel