BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Exam PRINCE2-Practitioner Topic 3 Question 19 Discussion

Actual exam question for PRINCE2's PRINCE2-Practitioner exam
Question #: 19
Topic #: 3
[All PRINCE2-Practitioner Questions]

During stage 3, the project scope was extended to include a practice test for learners to take during the training course. The cost of this test will be included in the cost of the course.

The change to project scope was approved and the cost of 2,500 was paid for from the change budget. The project manager documented an increase of 2,500 in the project budget in the business case.

Is this an appropriate action, and why?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel