BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Exam PRINCE2-Practitioner Topic 2 Question 72 Discussion

Actual exam question for PRINCE2's PRINCE2-Practitioner exam
Question #: 72
Topic #: 2
[All PRINCE2-Practitioner Questions]

MANAGING PRODUCT DELIVERY

Stage 2 is in progress. While producing the team plan, the team manager responsible for the work package to develop the 'classroom-based training material' discovered that the representatives assigned to check the products were unsuitable.

Which action should the team manager take in response?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Kanisha
1 months ago
I think raising an exception report to the project manager is the best course of action to address this issue.
upvoted 0 times
...
Percy
2 months ago
I hope the team manager has a good sense of humor, because this reminds me of that classic joke about the representatives being 'unsuitable' for the job. Hopefully, they can find a solution that's a little more 'classroom-based' than the problem itself!
upvoted 0 times
Buddy
22 days ago
C) Update the quality register with these concerns.
upvoted 0 times
...
Nicolette
25 days ago
B) Advise the project manager of this risk.
upvoted 0 times
...
Hubert
1 months ago
A) Discuss the situation with project assurance.
upvoted 0 times
...
...
Leatha
2 months ago
I believe updating the quality register with these concerns could also be a good option.
upvoted 0 times
...
Rosendo
2 months ago
I agree with Carlene, it's important to involve project assurance in such cases.
upvoted 0 times
...
Carlene
2 months ago
I think the team manager should discuss the situation with project assurance.
upvoted 0 times
...
Aja
2 months ago
Option D all the way! Raising an exception report is the way to go. The project manager needs to know about this issue before it becomes a bigger problem.
upvoted 0 times
Gerardo
13 days ago
D) Raise an exception report to the project manager.
upvoted 0 times
...
Brandon
14 days ago
C) Update the quality register with these concerns.
upvoted 0 times
...
Keneth
15 days ago
B) Advise the project manager of this risk.
upvoted 0 times
...
Chan
1 months ago
A) Discuss the situation with project assurance.
upvoted 0 times
...
...
Louann
2 months ago
Updating the quality register is a good idea, but it doesn't really solve the immediate problem. The team manager needs to take more direct action.
upvoted 0 times
...
Stanford
2 months ago
Discussing the situation with project assurance sounds like the right approach. They can provide guidance on how to handle this problem effectively.
upvoted 0 times
...
Gerald
2 months ago
I think the team manager should raise an exception report to the project manager. That's the best way to address this issue and get it resolved quickly.
upvoted 0 times
Son
1 months ago
B) Advise the project manager of this risk.
upvoted 0 times
...
Carey
1 months ago
A) Discuss the situation with project assurance.
upvoted 0 times
...
Melodie
1 months ago
B) Advise the project manager of this risk.
upvoted 0 times
...
Stephaine
2 months ago
B) Advise the project manager of this risk.
upvoted 0 times
...
Margarett
2 months ago
A) Discuss the situation with project assurance.
upvoted 0 times
...
Ruthann
2 months ago
A) Discuss the situation with project assurance.
upvoted 0 times
...
...

Save Cancel