BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Exam PRINCE2-Practitioner Topic 2 Question 17 Discussion

Actual exam question for PRINCE2's PRINCE2-Practitioner exam
Question #: 17
Topic #: 2
[All PRINCE2-Practitioner Questions]

As a result of experiences on previous projects, a change authority has been established for the Health and Safety Training Project. A key client for the training materials has a representative on the project board.

Should their interests be represented within the change authority for the project, and why?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel