BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Exam PRINCE2-Practitioner Topic 1 Question 52 Discussion

Actual exam question for PRINCE2's PRINCE2-Practitioner exam
Question #: 52
Topic #: 1
[All PRINCE2-Practitioner Questions]

The Sales Director would like to add a new company logo to the 'marketing material'. The change to the project scope has been approved by the project board. It is expected to delay product and stage completion date by 3 days and cost 900. The stage 2 cost tolerance of +1,000 has not been used. The change budget of 500 has not been used.

Which option describes how this change should be funded?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel