BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Exam PRINCE2-Foundation Topic 4 Question 92 Discussion

Actual exam question for PRINCE2's PRINCE2-Foundation exam
Question #: 92
Topic #: 4
[All PRINCE2-Foundation Questions]

Which statement about the length of management stages in a project is CORRECT?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Carmelina
24 days ago
You know, the project manager should just lock the project board in the conference room until they finish reviewing the stage gates. That would solve the problem!
upvoted 0 times
...
Adell
25 days ago
Haha, I bet the project board members are always trying to sneak out early for their tee times! Option B is probably the most realistic.
upvoted 0 times
...
Barb
26 days ago
D is also a good answer. Management stages provide a time-driven control mechanism for the project.
upvoted 0 times
...
Carri
1 months ago
I agree with Dong. Shorter stages allow for more frequent control checkpoints when you have higher risk.
upvoted 0 times
Remona
1 days ago
Shorter stages allow for more frequent control checkpoints when you have higher risk.
upvoted 0 times
...
Laurel
4 days ago
B) Stage length is influenced by project board availability
upvoted 0 times
...
Kati
15 days ago
A) A higher level of major risk will require a stage to be longer
upvoted 0 times
...
...
Dong
1 months ago
Option C makes the most sense. A higher level of risk should lead to shorter stages, so you can address issues more quickly.
upvoted 0 times
Oliva
3 days ago
I agree, shorter stages would allow for quicker problem-solving.
upvoted 0 times
...
...
Ceola
1 months ago
Why do you think that?
upvoted 0 times
...
Elinore
1 months ago
I disagree, I believe it's D)
upvoted 0 times
...
Ceola
2 months ago
I think the correct statement is A)
upvoted 0 times
...

Save Cancel