BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Exam PRINCE2-Foundation Topic 2 Question 96 Discussion

Actual exam question for PRINCE2's PRINCE2-Foundation exam
Question #: 96
Topic #: 2
[All PRINCE2-Foundation Questions]

Which process is used by the project board to respond to on exception report?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Pearlene
14 days ago
I think it's B) Managing a stage boundary. The project board would respond to an exception report as part of managing the transition between project stages.
upvoted 0 times
...
Jennifer
17 days ago
I agree with Alex, because managing a stage boundary involves reviewing and approving exception reports.
upvoted 0 times
...
Alex
22 days ago
I think the answer is B) Managing a stage boundary.
upvoted 0 times
...

Save Cancel