PRINCE2 Exam PRINCE2-Foundation Topic 2 Question 96 Discussion

Actual exam question for PRINCE2's PRINCE2-Foundation exam
Question #: 96
Topic #: 2
[All PRINCE2-Foundation Questions]

Which process is used by the project board to respond to on exception report?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Dorathy
2 months ago
Haha, the project board better not be 'Directing a project' like a bunch of clowns! I'd say B) Managing a stage boundary is the way to go.
upvoted 0 times
Kris
1 months ago
Directing a project does sound a bit too controlling.
upvoted 0 times
...
Maybelle
2 months ago
Managing product delivery could be a good option too.
upvoted 0 times
...
Dino
2 months ago
Yeah, Controlling a stage might be too restrictive.
upvoted 0 times
...
Timmy
2 months ago
I agree, Managing a stage boundary is the right choice.
upvoted 0 times
...
...
Micah
2 months ago
This is a tough one, but I'll go with C) Managing product delivery. The project board needs to ensure the successful delivery of products, which includes addressing any exceptions.
upvoted 0 times
...
Terrilyn
2 months ago
D) Directing a project seems more appropriate. The project board is responsible for providing overall direction and oversight, which includes responding to exception reports.
upvoted 0 times
Mammie
1 months ago
D) Directing a project
upvoted 0 times
...
Lauran
1 months ago
C) Managing product delivery
upvoted 0 times
...
Lashawn
2 months ago
B) Managing a stage boundary
upvoted 0 times
...
Yaeko
2 months ago
A) Controlling a stage
upvoted 0 times
...
...
Pearlene
3 months ago
I think it's B) Managing a stage boundary. The project board would respond to an exception report as part of managing the transition between project stages.
upvoted 0 times
Audry
2 months ago
Managing product delivery is also crucial for successful project completion.
upvoted 0 times
...
Candra
2 months ago
Yes, it helps ensure that any issues are addressed before moving on to the next stage.
upvoted 0 times
...
Tracey
2 months ago
It's important for the project board to take action during the transition between stages.
upvoted 0 times
...
Andra
2 months ago
I agree, managing a stage boundary is the correct process to respond to an exception report.
upvoted 0 times
...
...
Jennifer
3 months ago
I agree with Alex, because managing a stage boundary involves reviewing and approving exception reports.
upvoted 0 times
...
Alex
3 months ago
I think the answer is B) Managing a stage boundary.
upvoted 0 times
...