Actual exam question for PRINCE2's PRINCE2-Agile-Foundation exam
Question #: 47
Topic #: 1
[All PRINCE2-Agile-Foundation Questions]

Which well-known agile method uses visualization, and controls work in progress?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Florinda
5 months ago
You might be right, Dana. Pretty sure it's D) Kanban then.
upvoted 0 times
...
Colette
5 months ago
I think Kanban makes sense. They limit the tasks in each stage to avoid bottlenecks.
upvoted 0 times
...
Margo
5 months ago
Daily stand-ups are a good point, but they don't focus much on controlling work in progress.
upvoted 0 times
...
Florinda
5 months ago
Interesting point, I was considering Scrum because of the daily stand-ups.
upvoted 0 times
...
Tatum
5 months ago
I agree, but it sounds like Kanban to me. They use boards to visualize tasks.
upvoted 0 times
...
Margo
6 months ago
I think this one's tricky. Visualization and controlling work in progress, hmm...
upvoted 0 times
...

Save Cancel