Actual exam question for PRINCE2's PRINCE2-Agile-Foundation exam
Question #: 44
Topic #: 1
[All PRINCE2-Agile-Foundation Questions]

Which statement about the 'initiating a project' process is CORRECT?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Van
4 months ago
Yes, that's a good point. Quality management is key in any project.
upvoted 0 times
...
Lonny
4 months ago
I believe option B) The impact of frequent releases on quality management should be assessed is also important.
upvoted 0 times
...
Annabelle
4 months ago
That's also important, but I think having a solid initiation stage plan is crucial.
upvoted 0 times
...
Kiley
4 months ago
But what about option D) The project solution should be documented in detail in the project product description?
upvoted 0 times
...
Aleisha
5 months ago
I agree with that, it's important to have a clear plan from the start.
upvoted 0 times
...
Staci
5 months ago
I think the correct answer is A) The initiation stage plan should form part of the project plan.
upvoted 0 times
...
Arminda
5 months ago
I think the process should take more time for disruptive projects to ensure thorough planning and assessment.
upvoted 0 times
...
Edison
5 months ago
I agree with Kayleigh, detailing the project solution is crucial for clarity.
upvoted 0 times
...
Kayleigh
6 months ago
But shouldn't the project solution be documented in detail in the project product description?
upvoted 0 times
...
Eladia
6 months ago
I disagree, I believe the impact of frequent releases on quality management should be assessed.
upvoted 0 times
...
Kayleigh
6 months ago
I think the initiation stage plan should form part of the project plan.
upvoted 0 times
...

Save Cancel