PRINCE2 Exam PRINCE2-7-Foundation Topic 5 Question 4 Discussion

Actual exam question for PRINCE2's PRINCE2-7-Foundation exam
Question #: 4
Topic #: 5
[All PRINCE2-7-Foundation Questions]

The project manager needs to record the impact assessment for a specific business opportunity.

In which management product should the project manager record this?

Show Suggested Answer Hide Answer
Suggested Answer: A

The project manager should record the impact assessment for a specific business opportunity in an 'Issue Report'. This management product is used to detail particular issues that might affect the project, including opportunities (which are treated like positive risks), and provides a basis for decision-making regarding these issues. Reference: PRINCE2 7 Foundation materials on issue management and related documentation.


Contribute your Thoughts:

Willow
4 months ago
Risk register all the way! That's where you keep track of all the things that could go wrong and how much they'll hurt if they do. Perfect place for an impact assessment.
upvoted 0 times
Marla
2 months ago
D) Quality register
upvoted 0 times
...
Jolanda
2 months ago
C) Risk register
upvoted 0 times
...
Rene
3 months ago
B) Issue register
upvoted 0 times
...
Cherry
3 months ago
A) Issue report
upvoted 0 times
...
Darrin
3 months ago
D) Quality register
upvoted 0 times
...
Juan
3 months ago
C) Risk register
upvoted 0 times
...
Donte
3 months ago
B) Issue register
upvoted 0 times
...
Louis
3 months ago
A) Issue report
upvoted 0 times
...
...
Providencia
4 months ago
This is a tough one. I'm going to have to go with C) Risk register. It just makes the most sense to me. Unless, of course, the project manager is feeling particularly risky today and wants to record it in the 'Danger Zone' register.
upvoted 0 times
...
Lore
4 months ago
I agree with Lottie, recording it in the Quality register makes the most sense.
upvoted 0 times
...
Lottie
4 months ago
I think it should be in the Quality register, as it impacts the overall quality of the project.
upvoted 0 times
...
Ming
4 months ago
The quality register seems like an odd choice. I'd go with the risk register - that's where you keep track of all the potential issues and their impacts.
upvoted 0 times
Val
3 months ago
I think the issue register could also work, but the risk register is more comprehensive.
upvoted 0 times
...
Rodolfo
3 months ago
I agree, the risk register is the best option for recording impact assessments.
upvoted 0 times
...
...
Marica
4 months ago
Hmm, I'm not so sure. Wouldn't the issue register be a more appropriate place to document this kind of impact assessment?
upvoted 0 times
...
Shizue
4 months ago
I think the risk register would be the best place to record the impact assessment. It's all about managing risks, right?
upvoted 0 times
Lorenza
3 months ago
Definitely, it helps to have a centralized location for all project-related assessments.
upvoted 0 times
...
Jacquelyne
3 months ago
I think it's important to have all the information in one place for easy reference.
upvoted 0 times
...
Beula
3 months ago
Yes, the risk register is specifically designed to manage and track risks.
upvoted 0 times
...
Evangelina
3 months ago
I agree, the risk register is the best place to record the impact assessment.
upvoted 0 times
...
Lawrence
3 months ago
D) Quality register
upvoted 0 times
...
Ivan
3 months ago
C) Risk register
upvoted 0 times
...
Vallie
3 months ago
B) Issue register
upvoted 0 times
...
Margurite
4 months ago
A) Issue report
upvoted 0 times
...
...
Kenny
4 months ago
I disagree, I believe it should be recorded in the Issue register.
upvoted 0 times
...
Maile
5 months ago
I think the project manager should record it in the Risk register.