MultipleChoice
After the project charter's approval, the project manager needs to work on detailed project requirements, constraints, and assumptions with stakeholders. However, not all of the stakeholders are immediately available for a meeting in the short term.
What should the project manager do in order to gather the information needed from stakeholders?
OptionsMultipleChoice
According to this burnup chart for the last 7-day sprint, what should the project lead address with the product owner and team?
OptionsMultipleChoice
An agile team has sized all of the features for the release. Using the table above, how many sprints will it take to complete this release if the team is expecting to have a
velocity of 10 story points per sprint?
A 1
OptionsMultipleChoice
Which of the following is a measure of the value of work completed compared to the actual cost or progress made on the project?
OptionsMultipleChoice
The person assigned by the performing organization to be responsible for achieving the project objectives is the:
OptionsHotspot
A project is on its sixth iteration out of seven. Select the two points where the team is performing better than expected. (Choose two.)
MultipleChoice
A project manager is leading a software development project. Recently, team members have complained that during the last few dally standup meetings, a key stakeholder frequently interrupts, requests explanations, and proposes unplanned changes. This issue is frustrating the project team and slowing down me work.
What should the project manager do?
OptionsMultipleChoice
In an organization with good work-life balance, one team was continuously overloaded, thereby delivering the product late with poor quality. What should the project
manager do?
OptionsMultipleChoice
A project manager is leading three projects in a program focused on starting product commercialization. Once the three projects start going to market, the project manager stops attending the recurring team meetings. The program manager asks the project manager to continue attending these meetings to maintain those team touchpoints.
This request does not match the project manager's expectation, since a program manager is overseeing the remaining work
How should the project manager approach the situation?
OptionsMultipleChoice
The end point of a project phase can be referred to as:
Options