MultipleChoice
One team member is complaining about an agreement made during the last meeting. That team member was present at the meeting and participated in the decisions registered in the meeting minutes.
What should the project manager do next?
OptionsMultipleChoice
During initiation of a new product improvement project, a project manager finds historical data showing that a similar project resulted in customers complaining of an even worse user experience compared to the previous product version. How can the project manager prevent this outcome in the new project?
OptionsMultipleChoice
During the closing process, the project manager learns that one deliverable is not meeting customer expectations. How should the project manager proceed?
OptionsDragDrop
A production team will soon begin their first agile project. No one in the team or management has agile knowledge. The training manager can only fund three enrollments.
Match the team role on the left to the correct training course on the right. (Use all three of the team roles.)
MultipleChoice
A project is being executed. The project's life cycle is defined as predictive; however, a major deliverable will be handed over incrementally to the customer. The
assigned resources are experienced and reliable and are willing to make decisions that the project manager used to make after each incremental delivery on other
projects.
What should the project manager do?
OptionsMultipleChoice
Anew project manager was assigned to a project during implementation. The project manager realized that new tax policies are creating a risk for a cost overrun by 25%. The project manager updated the risk register and kept the project running as normal. The CEO has announced that the project could be cancelled since the acceptable cost overrun is only 20%. The project manager was quite surprised as this was new information.
What should the project manager have done to avoid this?
OptionsMultipleChoice
A project sponsor commonly asks the project manager to skip project retrospectives due to time constraints. However, the project manager persists in running this critical ceremony by reducing the time for preparation and for discussion.
What are two issues that these actions by the project manager could cause? (Choose two)
OptionsMultipleChoice
A project manager joins a team that is providing a customized enterprise resource planning (ERP) system to a client. A potential design problem is identified by the
development team. After reviewing this issue with the project owner and team members, all agreed to revise the design to avoid a system defect when deployed. The
design is already approved.
What should be the project manager's next steps?
OptionsMultipleChoice
A project manager is working with a Scrum team that is continually missing deadlines. The steering committee is concerned about the project as it is not clear that it will deliver the expected value. After some analysis, the project manager discovers there is a mismatch of competencies in one of the teams.
What should the project manager do?
OptionsMultipleChoice
In an industrial plant, the owner has decided to add more capacity to the plant by installing a new machine and updating the software used in production. This
capacity enlargement will occur while the plant is still functioning and producing. The software update will be accomplished using an agile approach in order to
minimize risk. The machine procurement, installation, and integration will be accomplished using predictive approaches.
What types of communications will the project manager have to design into the schedule management plan to ensure the project will be on schedule?
Options