Jenny is the project manager for the NBT projects. She is working with the project team and several subject matter experts to perform the quantitative risk analysis process. During this process she and the project team uncover several risks events that were not previously identified. What should Jenny do with these risk events?
OptionsMultipleChoice
Lisa is the project manager of the SQL project for her company. She has completed the risk response planning with her project team and is now ready to update the risk register to reflect the risk response. Which of the following statements best describes the level of detail Lisa should include with the risk responses she has created?
OptionsMultipleChoice
Which of the following documents is described in the statement below?
"It is developed along with all processes of the risk management. It contains the results of the qualitative risk analysis, quantitative risk analysis, and risk response planning."
OptionsMultipleChoice
Which of the following processes is described in the statement below?
"This is the process of numerically analyzing the effect of identified risks on overall project objectives."