Here you can find all the free questions related with PMI Agile Certified Practitioner (PMI-ACP) exam. You can also find on this page links to recently updated premium files with which you can practice for actual PMI Agile Certified Practitioner Exam. These premium versions are provided as PMI-ACP exam practice tests, both as desktop software and browser based application, you can use whatever suits your style. Feel free to try the PMI Agile Certified Practitioner Exam premium files for free, Good luck with your PMI Agile Certified Practitioner Exam.
Question No: 1

MultipleChoice

Midway through at iteration, an agile team learns that a team member will be unavailable for the next two iterations.

As a high-performance team, what should the team do?

Options
Question No: 2

MultipleChoice

Senior management is frustrated at the lack of a detailed implementation plan that shows exactly when the project will end and when all requirements will be met. The team has been using a rolling wave planning approach so far on the project.

How should the agile practitioner explain to senior management the benefits of this approach?

Options
Question No: 3

MultipleChoice

What can an agile team use to prioritize stories?

Options
Question No: 4

MultipleChoice

An agile team member from a cross-functional team has been unable to complete assignments due to tasks assigned by the functional manager.

What should the Scrum Master do?

Options
Question No: 5

MultipleChoice

The team is in the middle of an iteration and there is an urgent request for a small change to be introduced to the committed scope. Unless this change is accepted, there is no value to the customers during this iteration.

What must the agile practitioner do?

Options
Question No: 6

MultipleChoice

During a mature agile team's planning meeting, a team member proposes a new framework that would considerably reduce implementation time. However, the team lacks the confidence to try the new framework.

To help the team gain confidence, what should the agile practitioner suggest?

Options
Question No: 7

MultipleChoice

An agile practitioner wants to ensure that stakeholders have current information about a project's progress.

What should the agile practitioner do?

Options
Question No: 8

MultipleChoice

A product owner, new to the role, is very enthusiastic about an agile project with an energetic team.

What should be done first to ensure successful delivery of the product?

Options
Question No: 9

MultipleChoice

Two similar stories, A and B, are estimated at 3 story points. Story C, is estimated at 8 points. After an iteration in which A and C were completed, it is found that story A took much longer than story C.

What should the agile practitioner do?

Options
Question No: 10

MultipleChoice

During a current sprint, a team member asks permission from the scrum master to investigate an alternative design approach.

What should the scrum master do?

Options