You work as a project manager for BlueWell Inc. You are in the process of identifying all the people and organization impacted by the project. Mark, a project team member, has some doubts about the inputs of the Identify Stakeholder process. What is referred to as an input to the identify stakeholder process in project communication management?
The project charter is an input to the identify stakeholder process. It provides information about the
internal and external parties concerned
and is affected by the project.
The project charter is the document that formally authorizes a project. The project charter provides
the project manager with the authority to
apply organizational resources to project activities. According to PMBOK Guide, the project charter
should address the following information:
Requirements that satisfy customer, sponsor, and other stakeholder needs, wants and expectations
Business needs, high-level project description, or product requirements that the project is
undertaken to address
Project purpose or justification
Assigned Project Manager and authority level
Summary milestone schedule
Stakeholder influences
Functional organizations and their participation
Organizational, environmental and external assumptions
Organizational, environmental and external constraints
Business case justifying the project, including return on investment
Summary budget
If required, it also authorizes the next project phase, and updates the charter. The project manager
should always be assigned prior to the
start of planning, and preferably while the project charter is being developed.
Answer option A is incorrect. Expert judgment is a technique based on a set of criteria that has been
acquired in a specific knowledge area or
product area. It is obtained when the project manager or project team requires specialized
knowledge that they do not possess. Expert
judgment involves people most familiar with the work of creating estimates. Preferably, the project
team member who will be doing the task
should complete the estimates. Expert judgment is applied when performing administrative closure
activities, and experts should ensure the
project or phase closure is performed to the appropriate standards.
Answer option C is incorrect. Stakeholder analysis is the identification of stakeholder needs, wants
and expectations. It involves the
documentation, prioritization, and quantification of the needs to help define the project scope.
Stakeholders' interests may be positively or
negatively affected by execution or completion of the project and they may also exert influence over
the project and its deliverables.
Answer option D is incorrect. The stakeholder register is a project management document that
contains a list of the stakeholders associated
with the project. It assesses how they are involved in the project and identifies what role they play in
the organization. The information in this
document can be very perceptive and is meant for limited exchange only. It also contains relevant
information about the stakeholders, such as
their requirements, expectations, and influence on the project.
Della works as a Project Manager for Blue Well Inc. A number of projects are running under her guidance. You, being a team leader of a project, provide Della the performance indexes of your project. The schedule variance (SV) of your project is zero. What does this figure depict?
According to the question, the schedule variance (SV) of the project is zero. A value of 0
indicates that the project is right on target.
Schedule variance (SV) is a measure of schedule performance on a project. The variance notifies that
the schedule is ahead or behind what
was planned for this period in time. The schedule variance is calculated based on the following
formula:
SV = Earned Value (EV) - Planned Value (PV)
If the resulting schedule is negative, it indicates that the project is behind schedule. A value greater
than 0 shows that the project is ahead of
the planned schedule. A value of 0 indicates that the project is right on target.
Answer option C is incorrect. The negative SV means that project is behind the schedule.
Answer option D is incorrect. This result can be drawn by looking at the cost variance (CV) of the
project.
Answer option B is incorrect. The positive SV depicts that the project is ahead of the planned
schedule.
Examine the figure given below: Which path is considered the critical path?
The critical path is the path in the project network diagram with the longest duration. In project management, a critical path is the sequence of project network activities which add up to the longest overall duration. This determines the shortest time possible to complete the project. Any delay of an activity on the critical path directly impacts the planned project completion date (i.e. there is no float on the critical path). In this instance path ACGIJ is the longest as it takes 23 days.
Answer options C and D are incorrect. These paths take 13 days. Answer option A is incorrect. This path only takes 19 days.
Beth is the project manager for her organization. Her current project has many deliverables that have been defined at a high level, but the details of the deliverables are still unknown. In her project, Beth is planning in detail only the activities that are most imminent in the project work. This approach to project management planning is known as what?
Rolling wave planning is a technique to plan and do the most imminent project work before moving onto the details that are far off in the project schedule and project plan. Rolling wave planning is a technique for performing progressive elaboration planning where the work to be accomplished in the near future is planned in detail at a low level of the work breakdown structure. The work to be performed within another one or two reporting periods in the near future is planned in detail as work is being completed during the current period. Answer option D is incorrect. Decomposition is the process of breaking down work packages into the activity list. Answer options A and C are incorrect. These are not valid project management terms.
You are the project manager for your organization. You are working with your project team to
develop the project schedule. You would like to automate much of the scheduling by using Microsoft
project. Microsoft project as a scheduling tool is an example of what tool and technique for the
Develop Schedule Process?
According to the PMBOK, automated scheduling tools expedite the scheduling process.
The scheduling tool is used in combination with manual methods or further project management
software to carry out the schedule network
analysis to produce an updated project schedule.
Answer option C is incorrect. The project management information system is the complete project
management software package beyond just
the scheduling portion.
Answer option D is incorrect. This is not a valid answer.
Answer option A is incorrect. While the software may be made available as a part of organizational
process assets, the best answer is the
scheduling tool.
Susy
14 days agoEstrella
23 days agoJacquline
2 months agoArmanda
2 months agoJade
3 months agoCary
3 months agoBlondell
4 months agoWillie
4 months agoDanica
4 months agoGearldine
5 months agoKeva
5 months agoShawnna
5 months agoPeggie
5 months agoMaryln
6 months agoKassandra
6 months agoNoel
6 months agoKayleigh
7 months agoUna
7 months agoTegan
7 months agoDarell
7 months agoJesusa
7 months agoJoaquin
7 months agoNovella
8 months agoSage
8 months agoWenona
8 months agoMicheal
9 months agoHester
9 months agoKris
9 months agoArmando
9 months agoDanica
10 months agoNadine
10 months agoJonell
10 months agoFlo
11 months agoBarabara
11 months agoAnglea
1 years agoFlo
1 years ago