A key project is delayed and all contingency reserves have been used even though the project team has implemented all planned risk responses. What should the risk manager do next?
You are the project manager for your organization. You have determined that an activity is too dangerous to complete internally so you hire licensed contractor to complete the work. The contractor, however, may not complete the assigned work on time which could cause delays in subsequent work beginning. This is an example of what type of risk event?
Fill in the blank with an appropriate phrase.
The _________ is the risk or danger of an action or an event, a method or a (technical) process that still conceives these dangers even if all theoretically possible safety measures would be applied.
Which of the following processes must be repeated after Plan Risk Responses, as well as part of the Monitor and Control Risks, to determine if the overall project risk has been satisfactorily decreased?
You work as a project manager for TechSoft Inc. You are working with the project stakeholders on the qualitative risk analysis process in your project. You have used all the tools to the qualitative risk analysis process in your project. Which of the following techniques is NOT used as a tool in qualitative risk analysis process?
Rolande
4 days agoShannon
5 days agoHollis
13 days agoJesusa
29 days agoFannie
1 months agoTijuana
1 months agoMozelle
1 months agoHester
2 months agoLashunda
2 months agoCarman
2 months agoMoon
3 months agoMarlon
4 months agoLanie
4 months agoEvelynn
5 months ago