The project team is updating the risk register with the minimum acceptable level of exposure and impact for each risk. The team also wants to determine if they have reached the maximum level of exposure before they escalate the risk.
What should the team perform in this scenario?
Quantitative risk analysis helps determine the minimum acceptable level of exposure and impact for each risk. It also helps to understand if the maximum level of exposure has been reached before escalating the risk. (Reference: PMBOK Guide, 6th Edition, p. 423)
The team should perform quantitative risk analysis, which is the process of numerically analyzing the effect of identified risks on overall project objectives. Quantitative risk analysis can help the team to establish the minimum acceptable level of exposure and impact for each risk, as well as the maximum level of exposure before escalation. Quantitative risk analysis can also provide probabilistic estimates of project outcomes, such as cost and schedule, and support risk prioritization and decision making.Reference:PMI, A Guide to the Project Management Body of Knowledge (PMBOK Guide), Sixth Edition, 2017, p. 399; PMI, The Standard for Risk Management in Portfolios, Programs, and Projects, 2019, p. 69.
A risk manager celebrates with team members after successfully resolving a major threat to the project schedule. However, the project sponsor was upset that the risk manager celebrated the risk response.
What should the risk manager have done before considering the risk response a success?
An organization is executing two projects---Project A and Project B---simultaneously A previously identified risk will impact the schedule for Project
A software development project team was preparing for a phased release when an unknown and unexpected risk occurred with potential for delaying one of the features for the planned release. The project team decided to go ahead with the release and address this missing feature at a later date. One of the end users learned about this and strongly opposed the planned release.
What should the risk manager have done to prevent this situation?
In a highly dynamic project environment, the project manager is known to have project risks as a permanent agenda item in their periodic project progress meetings. How will this help improve the project's risk management activities? (Choose 3)
Lawrence
7 days agoKristeen
8 days agoOctavio
22 days agoMila
1 months agoMonte
1 months agoFlorinda
2 months agoEvangelina
2 months agoTruman
2 months agoDouglass
2 months agoHoney
3 months agoDeonna
3 months agoLashon
3 months agoVerona
4 months agoAilene
4 months agoRolf
4 months agoRana
4 months agoNieves
4 months agoGail
5 months agoEvette
5 months agoRolande
5 months agoShannon
5 months agoHollis
5 months agoJesusa
6 months agoFannie
6 months agoTijuana
6 months agoMozelle
6 months agoHester
6 months agoLashunda
7 months agoCarman
7 months agoMoon
7 months agoMarlon
8 months agoLanie
9 months agoEvelynn
9 months ago