Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMP Topic 3 Question 88 Discussion

Actual exam question for PMI's PMP exam
Question #: 88
Topic #: 3
[All PMP Questions]

After a project has been approved, a key stakeholder tells the project manager that the current project management strategy is not well defined The project manager is also informed that the key stakeholder does not want to hold a working session

What should the project manager do first?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Ranee
2 months ago
A) The diplomatic approach is usually the best policy. Unless of course the key stakeholder is a raving lunatic - then all bets are off!
upvoted 0 times
Willow
13 days ago
D) Inviting the key stakeholder to the change control board might be a good way to address the issue
upvoted 0 times
...
Mi
16 days ago
C) Proceeding with a working session for other teams could help clarify the strategy
upvoted 0 times
...
Melvin
18 days ago
B) I agree, it's important to address the concerns early on
upvoted 0 times
...
Laura
22 days ago
A) Share the project documents and invite the key stakeholder to discuss any concerns
upvoted 0 times
...
...
Geraldine
2 months ago
I disagree. I think the project manager should go with option D and invite the key stakeholder to the project's change control board to discuss adjustment of the project strategy.
upvoted 0 times
...
Val
2 months ago
B) Asking the project sponsor to step in is a bold move. Gotta love a little office politics to spice things up! Just don't get caught in the crossfire.
upvoted 0 times
Janella
1 months ago
A) Share the project documents and invite the key stakeholder to discuss any concerns
upvoted 0 times
...
Willard
1 months ago
D) Invite the key stakeholder to the project's change control board (CCB) to discuss adjustment of the project strategy
upvoted 0 times
...
Natalie
1 months ago
B) Asking the project sponsor to step in is a bold move. Gotta love a little office politics to spice things up! Just don't get caught in the crossfire.
upvoted 0 times
...
Vi
2 months ago
D) Invite the key stakeholder to the project's change control board (CCB) to discuss adjustment of the project strategy
upvoted 0 times
...
Francoise
2 months ago
B) Asking the project sponsor to step in is a bold move. Gotta love a little office politics to spice things up! Just don't get caught in the crossfire.
upvoted 0 times
...
Claudio
2 months ago
A) Share the project documents and invite the key stakeholder to discuss any concerns
upvoted 0 times
...
Felix
2 months ago
A) Share the project documents and invite the key stakeholder to discuss any concerns
upvoted 0 times
...
...
Ena
2 months ago
I agree with Fletcher. Sharing project documents and discussing concerns with the key stakeholder is the best approach.
upvoted 0 times
...
Fletcher
3 months ago
I think the project manager should choose option A.
upvoted 0 times
...
Alesia
3 months ago
C) Proceeding with a working session for the other teams seems like a sneaky way to sideline the key stakeholder. Not very constructive in the long run.
upvoted 0 times
...
Katina
3 months ago
D) Inviting the key stakeholder to the CCB is a great way to address the issue formally and get everyone on the same page. Hopefully they don't try to 'exert their authority' like a playground bully.
upvoted 0 times
Kristeen
2 months ago
C) Proceed with a working session for teams that do not belong to that key stakeholder
upvoted 0 times
...
Ira
2 months ago
A) That sounds like a good plan. It's important to address the issue formally and get everyone on the same page.
upvoted 0 times
...
Ernest
2 months ago
D) Invite the key stakeholder to the project's change control board (CCB) to discuss adjustment of the project strategy
upvoted 0 times
...
Kaycee
3 months ago
A) Share the project documents and invite the key stakeholder to discuss any concerns
upvoted 0 times
...
...
Anglea
3 months ago
A) Sharing the project documents and inviting the key stakeholder to discuss any concerns sounds like the most diplomatic approach. I don't want to ruffle any feathers here.
upvoted 0 times
Charlene
2 months ago
D) Invite the key stakeholder to the project's change control board (CCB) to discuss adjustment of the project strategy
upvoted 0 times
...
Latosha
2 months ago
A) Sharing the project documents and inviting the key stakeholder to discuss any concerns sounds like the most diplomatic approach. I don't want to ruffle any feathers here.
upvoted 0 times
...
...

Save Cancel