After a project has been approved, a key stakeholder tells the project manager that the current project management strategy is not well defined The project manager is also informed that the key stakeholder does not want to hold a working session
What should the project manager do first?
Ranee
20 days agoGeraldine
1 months agoVal
1 months agoJanella
7 days agoWillard
10 days agoNatalie
13 days agoVi
22 days agoFrancoise
23 days agoClaudio
24 days agoFelix
28 days agoEna
1 months agoFletcher
2 months agoAlesia
2 months agoKatina
2 months agoKristeen
27 days agoIra
1 months agoErnest
1 months agoKaycee
2 months agoAnglea
2 months agoCharlene
1 months agoLatosha
1 months ago