After a project has been approved, a key stakeholder tells the project manager that the current project management strategy is not well defined The project manager is also informed that the key stakeholder does not want to hold a working session
What should the project manager do first?
Ranee
2 months agoWillow
13 days agoMi
16 days agoMelvin
18 days agoLaura
22 days agoGeraldine
2 months agoVal
2 months agoJanella
1 months agoWillard
1 months agoNatalie
1 months agoVi
2 months agoFrancoise
2 months agoClaudio
2 months agoFelix
2 months agoEna
2 months agoFletcher
3 months agoAlesia
3 months agoKatina
3 months agoKristeen
2 months agoIra
2 months agoErnest
2 months agoKaycee
3 months agoAnglea
3 months agoCharlene
2 months agoLatosha
2 months ago