The project manager just started loading a project team from which the previous project manager resigned. After a quick evaluation of the project, it is apparent that team morale is low due to continuous disagreement about how to complete tasks. Tasks are taking longer than forecasted and the project is off schedule.
What should the project manager do?
Timothy
8 months agoMaryann
8 months agoTalia
8 months agoTimothy
8 months agoMaryann
8 months agoCharlesetta
8 months agoBilli
8 months agoAfton
9 months agoDelsie
9 months agoCherelle
10 months agoLettie
10 months agoKiley
11 months agoIlene
11 months agoGolda
11 months agoMa
10 months agoLashon
10 months agoHarley
10 months agoNovella
10 months agoIzetta
11 months ago