The project manager just started loading a project team from which the previous project manager resigned. After a quick evaluation of the project, it is apparent that team morale is low due to continuous disagreement about how to complete tasks. Tasks are taking longer than forecasted and the project is off schedule.
What should the project manager do?
Timothy
9 months agoMaryann
9 months agoTalia
9 months agoTimothy
9 months agoMaryann
10 months agoCharlesetta
10 months agoBilli
10 months agoAfton
10 months agoDelsie
10 months agoCherelle
11 months agoLettie
11 months agoKiley
12 months agoIlene
12 months agoGolda
12 months agoMa
11 months agoLashon
11 months agoHarley
11 months agoNovella
12 months agoIzetta
1 years ago