Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMP Topic 3 Question 65 Discussion

Actual exam question for PMI's PMP exam
Question #: 65
Topic #: 3
[All PMP Questions]

A company plans to initiate a project involving a new technology. Approval for the project is required. What should the project manager do?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel