BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMP Topic 3 Question 62 Discussion

Actual exam question for PMI's PMP exam
Question #: 62
Topic #: 3
[All PMP Questions]

A project manager for a software development company faces a number of financial risks in their project. The project manager needs to frequently check the strength and

efficiency of the risk management process.

What should the project manager use to accomplish this?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel