Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMP Topic 3 Question 6 Discussion

Actual exam question for PMI's PMP exam
Question #: 6
Topic #: 3
[All PMP Questions]

During a portfolio review meeting, a project manager teams that their project was cancelled. The project manager wants to inform stakeholders and team members about this

To what document should the project manager refer?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel