Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMP Topic 3 Question 55 Discussion

Actual exam question for PMI's PMP exam
Question #: 55
Topic #: 3
[All PMP Questions]

A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource

for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a

leave.

What should the project manager do next?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel