PMI Exam PMP Topic 3 Question 32 Discussion

Actual exam question for PMI's PMP exam
Question #: 32
Topic #: 3
[All PMP Questions]

A project manager has been asked to participate in the procurement process for a

software application that allows customers to buy online e-learning courses. The project

manager will take over the project once the supplier has been sourced.

What should the project manager do before the project starts?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!