Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMP Topic 3 Question 3 Discussion

Actual exam question for PMI's PMP exam
Question #: 3
Topic #: 3
[All PMP Questions]

A project manager notices that the project is behind schedule because materials delivery was delayed. The procurement team informs the project manager that new government-imposed rules for the procurement of these materials caused this delay.

In what plan should these new rules be documented?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel