Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMP Topic 3 Question 28 Discussion

Actual exam question for PMI's PMP exam
Question #: 28
Topic #: 3
[All PMP Questions]

A company has agreed to run a transformation project using agile approaches.

During the implementation, there is pushback from the functional groups that the project is moving too fast.

What should the project manager have done at the beginning of the project to prevent this from happening?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel