Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMP Topic 2 Question 99 Discussion

Actual exam question for PMI's PMP exam
Question #: 99
Topic #: 2
[All PMP Questions]

The project team is experiencing schedule delays due to issues arising with suppliers. Some of the tasks are on the critical path.

What should the project manager do in this situation?

Show Suggested Answer Hide Answer

Contribute your Thoughts:

Polly
2 days ago
D) Discussing the critical path issues with the purchasing department could help, but I think C) is the most comprehensive solution.
upvoted 0 times
...
Chandra
4 days ago
A) Escalating the supplier-related issues to the sponsor is a smart move. They can apply more pressure to resolve the problems.
upvoted 0 times
...
Audry
12 days ago
C) Review the critical path with the stakeholders to define next steps. This seems like the best approach to tackle the schedule delays caused by supplier issues.
upvoted 0 times
Arminda
2 days ago
B) Review the work breakdown structure (WBS) with the suppliers.
upvoted 0 times
...
Amber
4 days ago
A) Escalate the supplier-related issues to the sponsor for resolution.
upvoted 0 times
...
...

Save Cancel