Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMP Topic 2 Question 97 Discussion

Actual exam question for PMI's PMP exam
Question #: 97
Topic #: 2
[All PMP Questions]

During the release of an important product, a vice president for a different product line brought a valid concern to the project team, which had to be completed before the release. The vice president has not participated in other product discussions until now. This additional work resulted in a delay of the product release.

How should the project manager have handled this situation earlier in the project?

Show Suggested Answer Hide Answer
Suggested Answer: A

When faced with a situation where a vice president from a different product line brings a valid concern during the release of an important product, the project manager should have proactively identified the vice president as a stakeholder. Here's why:

1. Stakeholder Identification:

o Identifying stakeholders is a critical step in project management.

o Stakeholders include anyone who has an interest in or can be affected by the project.

o The vice president's involvement in the project, even if not previously engaged, makes them a relevant stakeholder.

2. Benefits of Identifying Stakeholders:

o Recognizing the vice president as a stakeholder allows the project manager to consider their concerns and priorities.

o It facilitates effective communication and collaboration throughout the project lifecycle.

o Stakeholder engagement ensures that all relevant perspectives are considered.

3. Risk Mitigation:

o By identifying the vice president as a stakeholder early on, the project manager could have addressed their concerns proactively.

o Recording the concerns in the risk register (Option B) is also valuable, but stakeholder identification comes first.

4. Project Boundaries and Scope:

o Sharing project boundaries and scope (Option D) is essential, but it doesn't directly address the vice president's concerns.

o Escalating dissent to top management (Option C) should be a last resort after attempting to resolve issues at lower levels.

In summary, identifying the vice president as a stakeholder would have allowed the project manager to engage them effectively, address their concerns, and prevent delays in the product release.


* [Delivering business value: The most important aspect of project management

Contribute your Thoughts:

Britt
19 days ago
Haha, the project manager should have bribed the vice president with a lifetime supply of donuts. Then maybe they would have stayed out of it!
upvoted 0 times
Jeannine
5 days ago
A) Identified the vice president as a stakeholder
upvoted 0 times
...
...
Noel
21 days ago
D seems like the way to go. Clearly defining the project boundaries and scope would have set the right expectations and avoided this last-minute change.
upvoted 0 times
B) Recorded the vice president's concerns in the risk register
upvoted 0 times
...
Kimberely
13 days ago
A) Identified the vice president as a stakeholder
upvoted 0 times
...
...
Isaiah
30 days ago
I think B is the right answer. Recording the vice president's concerns in the risk register would have helped the team anticipate and plan for this issue.
upvoted 0 times
Salena
7 days ago
B) Recorded the vice president's concerns in the risk register
upvoted 0 times
...
Nguyet
8 days ago
A) Identified the vice president as a stakeholder
upvoted 0 times
...
...
Michael
2 months ago
I think recording the vice president's concerns in the risk register would have also been helpful to track potential issues.
upvoted 0 times
...
Kenny
2 months ago
I agree with Basilia, it's important to involve all stakeholders from the beginning.
upvoted 0 times
...
Blair
2 months ago
The correct answer is A. The project manager should have identified the vice president as a stakeholder early on. Without involving all key stakeholders, the project is doomed to face such challenges.
upvoted 0 times
Maurine
2 days ago
D) Shared project boundaries so that everyone was aware of the scope
upvoted 0 times
...
Micaela
3 days ago
C) Escalated any dissent to top management right away
upvoted 0 times
...
Ressie
4 days ago
B) Recorded the vice president's concerns in the risk register
upvoted 0 times
...
Elfriede
5 days ago
A) Identified the vice president as a stakeholder
upvoted 0 times
...
...
Basilia
2 months ago
The project manager should have identified the vice president as a stakeholder.
upvoted 0 times
...

Save Cancel