A recently concluded quality audit failed and came back with multiple action items. A newly appointed project manager is reviewing the project status with the team. New stakeholders have been identified, and new audit resources may have to be added to the project.
What should the project manager do next?
When faced with the aftermath of a failed quality audit, the newly appointed project manager must take several steps to address the situation. Let's explore the options:
1. Perform Integrated Change Control (Option B):
o Integrated change control is a critical process in project management.
o It involves reviewing all change requests, assessing their impact, and making informed decisions about whether to approve or reject them.
o In this case, the failed audit results constitute a change request. The project manager should evaluate the impact of the audit findings, identify necessary corrective actions, and determine whether additional resources (such as new audit resources) are required.
o By performing integrated change control, the project manager ensures that any necessary adjustments are made to the project plan, scope, schedule, and resources.
2. Stakeholder Engagement (Option A):
o While stakeholder engagement is essential, it is not the immediate next step after a failed audit.
o Stakeholder engagement involves ongoing communication and collaboration with stakeholders throughout the project lifecycle.
o The project manager should engage stakeholders, but addressing the audit findings takes precedence.
3. Update the Quality Management Plan (Option C):
o Updating the quality management plan is relevant, but it is a specific response to the audit results.
o The project manager should first assess the impact of the audit findings and then update the quality management plan as needed.
4. Update the Risk Management Plan (Option D):
o While risk management is crucial, it is not the immediate focus after a failed audit.
o The project manager should address the audit findings before revisiting the risk management plan.
In summary, the project manager should prioritize integrated change control to address the audit results, identify corrective actions, and
Cammy
2 hours agoLuann
3 days agoFausto
5 days agoJudy
15 days agoIsidra
15 days agoLonna
4 days agoLouvenia
21 days agoLisbeth
6 days ago