Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMP Topic 2 Question 92 Discussion

Actual exam question for PMI's PMP exam
Question #: 92
Topic #: 2
[All PMP Questions]

A project is halfway through its execution phase. The quality specifications for the project deliverables are formally accepted. However, a key stakeholder is dissatisfied, stating that the deliverables do not meet the quality specifications.

What should the project manager do in this situation?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Raymon
1 days ago
We need to address the stakeholder's concerns.
upvoted 0 times
...

Save Cancel