Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMP Topic 2 Question 84 Discussion

Actual exam question for PMI's PMP exam
Question #: 84
Topic #: 2
[All PMP Questions]

A project manager is using a hybrid approach for project delivery. The

development team was sized, but is not yet fully resourced. The project manager is working

on defining the project schedule.

What should the project manager do to address the issue of developer availability?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Giuseppe
1 days ago
I think the project manager should organize a planning session with the development team.
upvoted 0 times
...

Save Cancel