Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMP Topic 2 Question 73 Discussion

Actual exam question for PMI's PMP exam
Question #: 73
Topic #: 2
[All PMP Questions]

A customer requests additional changes 1 day before the planned change date. How should the project manager respond to the change request?

Show Suggested Answer Hide Answer
Suggested Answer: C

According to the PMBOK Guide, the project manager should manage the project scope, including the planning, validation, and control of the scope. The project manager should also manage the project changes, including the initiation, evaluation, approval, and implementation of the changes. In this scenario, the project manager received a request to add additional changes 1 day before the planned change date. This is a potential change to the project scope that may also impact the project time, cost, quality, and other aspects. The best course of action is to review the additional changes and perform integrated change control. This can help the project manager to assess the feasibility and desirability of the change request, and to determine the appropriate response and approval. Reviewing the additional changes and performing integrated change control (option C) is the best solution to the issue, as it demonstrates proactive and effective project scope and change management. Rejecting the changes as the lead time is too short (option A) may not be feasible or ethical, as it may violate the customer's expectations and satisfaction, and may damage the trust and relationship with the customer. Determining whether the project team is capable of making the changes (option B) may not be sufficient or realistic, as it may ignore or overlook the impact and value of the change request, and may create a conflict or resentment among the project team. Checking if the changes are covered in the statement of work (SOW) (option D) may not be relevant or helpful, as it may not address the change request itself, nor does it account for the possible deviations or changes that may occur during the project execution.Reference: : Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK Guide) (6th ed.).Newtown Square, PA: Author1: Change Request - Project Management Knowledge2: Managing Change Requests in Project Management [Template]3: Which Project Documents Need A Change Request For Updates?4


Contribute your Thoughts:

Walker
5 months ago
I agree with we need to assess if our team can handle the changes.
upvoted 0 times
...
Willow
5 months ago
But the lead time is too short, shouldn't we reject the changes?
upvoted 0 times
...
Kizzy
5 months ago
I think we should review the changes and do integrated change control.
upvoted 0 times
...
Willow
6 months ago
I can't believe the customer wants changes at the last minute!
upvoted 0 times
...
Lawrence
6 months ago
I agree with Verlene, we need to check if the project team is capable of making the changes first.
upvoted 0 times
...
Rashida
7 months ago
But what if the lead time is too short? Shouldn't we reject the changes?
upvoted 0 times
...
Mabel
7 months ago
Yeah, it's important to ensure all changes are properly documented and approved.
upvoted 0 times
...
Verlene
7 months ago
I think the project manager should review the changes and perform integrated change control.
upvoted 0 times
...
Pearlene
7 months ago
I can't believe the customer wants changes so last minute.
upvoted 0 times
...
Cary
8 months ago
Ugh, last-minute changes are the bane of my existence. But I guess we have to be professional about it. Personally, I'd lean towards the integrated change control option - that way we can really assess the impact and decide if it's worth it.
upvoted 0 times
Leonor
7 months ago
Rejecting changes with short lead time is a valid option to maintain project timelines.
upvoted 0 times
...
Tawna
8 months ago
If the changes are not in the statement of work, we may need to reject them.
upvoted 0 times
...
Markus
8 months ago
Let's review the changes and see if they align with the original scope of work.
upvoted 0 times
...
Stefany
8 months ago
Integrated change control allows us to evaluate the changes properly.
upvoted 0 times
...
Cory
8 months ago
We need to make sure the project team can handle the additional changes.
upvoted 0 times
...
Iraida
8 months ago
It's important to assess the impact before agreeing to any changes.
upvoted 0 times
...
Lisbeth
8 months ago
Agreed, last-minute changes are always a challenge.
upvoted 0 times
...
...
Diego
8 months ago
Hmm, I'm with Precious on this one. We should definitely review the changes and see if they're within the scope of the SOW. If they are, then I think we have to at least consider making them happen. But if it's going to be a total mess, then yeah, we should probably nip it in the bud.
upvoted 0 times
...
Precious
8 months ago
Well, I think the key is to really evaluate if the project team can actually pull off those changes in time. If they're up for the challenge, then maybe we should go for it. But if it's going to be a major headache, then I'd be inclined to shut it down.
upvoted 0 times
...
Ciara
8 months ago
Oh man, this question is tough! We all know that last-minute changes can be a real pain in the neck. I'm tempted to just say 'Reject it and be done with it', but I guess we have to consider the options here.
upvoted 0 times
...

Save Cancel