Question #: 51
Topic #: 2
[All PMP Questions]

A large multi-national company works on a project in an emerging-economy country. All business matters are conducted in local currency. During the course of the project,

the budget becomes the primary concern due to currency instability in the country.

What should the project manager do next?

Show Suggested Answer Hide Answer
Suggested Answer: C