BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMP Topic 2 Question 47 Discussion

Actual exam question for PMI's PMP exam
Question #: 47
Topic #: 2
[All PMP Questions]

Two teams are engaged on a global project which uses a follow-the-sun approach in order to speed up delivery. After the first release, many issues were identified on the product, which could easily have been avoided with better communication.

What should the project manager do?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel