BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMP Topic 2 Question 40 Discussion

Actual exam question for PMI's PMP exam
Question #: 40
Topic #: 2
[All PMP Questions]

A project team is in the planning stage and has prepared a list of activities and completed sequencing the activities. During a review, the team noted that there is a

dependency missing between:

+ Test the product

+ Release to customer

According to the quality management plan, the product must be tested before being released.

How should the project manager enter this dependency?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel