Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMP Topic 2 Question 35 Discussion

Actual exam question for PMI's PMP exam
Question #: 35
Topic #: 2
[All PMP Questions]

An agile team was hired to work on a public service project. The team received a

list of vague ideas about the business and now needs to understand, develop, and prioritize a

list of functionalities.

Who will be responsible for this task?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel