BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMP Topic 2 Question 30 Discussion

Actual exam question for PMI's PMP exam
Question #: 30
Topic #: 2
[All PMP Questions]

A product owner has provided the team with a prioritized backlog for the initial

launch of a new product. After analysis, the team concludes that some work is missing to

support the initial launch and provides this information to the product owner. The product

owner acknowledges the missing work and adds it to the bottom of the backlog. The team is

not happy with the prioritization that the missing work received.

What should the project manager do in this situation?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel