Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMP Topic 1 Question 95 Discussion

Actual exam question for PMI's PMP exam
Question #: 95
Topic #: 1
[All PMP Questions]

In an agile environment, a project is running iteration four out of six. A team member leaves the company with no replacement.

What should the project manager do?

Show Suggested Answer Hide Answer
Suggested Answer: A

According to the PMBOK Guide, an issue log is a project document that records problems in a project and how they are resolved. A resource management plan is a component of the project management plan that describes how resources will be estimated, acquired, developed, managed, and controlled. When a team member leaves the company, the project manager should update the issue log with the details of the problem and the impact on the project. Then, the project manager should refer to the resource management plan to find out how to deal with the resource gap, such as reassigning tasks, hiring a new team member, or requesting additional resources from the sponsor or other stakeholders.


PMBOK Guide, 6th edition, pages 89-90, 318-319, 374-375

Agile Practice Guide, pages 32-33, 77-78

Contribute your Thoughts:

Vivan
8 days ago
I think the project manager should update the issue log and refer to the resource management plan.
upvoted 0 times
...

Save Cancel