Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMP Topic 1 Question 95 Discussion

Actual exam question for PMI's PMP exam
Question #: 95
Topic #: 1
[All PMP Questions]

In an agile environment, a project is running iteration four out of six. A team member leaves the company with no replacement.

What should the project manager do?

Show Suggested Answer Hide Answer
Suggested Answer: A

According to the PMBOK Guide, an issue log is a project document that records problems in a project and how they are resolved. A resource management plan is a component of the project management plan that describes how resources will be estimated, acquired, developed, managed, and controlled. When a team member leaves the company, the project manager should update the issue log with the details of the problem and the impact on the project. Then, the project manager should refer to the resource management plan to find out how to deal with the resource gap, such as reassigning tasks, hiring a new team member, or requesting additional resources from the sponsor or other stakeholders.


PMBOK Guide, 6th edition, pages 89-90, 318-319, 374-375

Agile Practice Guide, pages 32-33, 77-78

Contribute your Thoughts:

Zana
7 days ago
If the project manager asks the team for extra work (option B), they'd better start looking for a new job. That's a surefire way to lose your team and derail the project.
upvoted 0 times
...
Virgie
8 days ago
I'm surprised option A is even an option. Updating the issue log is great, but it doesn't actually solve the problem of a missing team member. The project manager needs to take action, not just document the issue.
upvoted 0 times
...
Eric
14 days ago
Option B is a terrible idea. Asking the team for extra work is just going to burn them out. The project manager should be finding ways to ease the burden, not add to it.
upvoted 0 times
Trinidad
10 days ago
A) Update the issue log and refer to the resource management plan to address the situation.
upvoted 0 times
...
...
Cristy
23 days ago
I believe asking the sponsor for an experienced team member would also be a good option to consider.
upvoted 0 times
...
Leila
23 days ago
I'd go with option D. Bringing in an experienced team member from the company is the smartest move. The project team needs all the help they can get to stay on track.
upvoted 0 times
Jesusita
6 days ago
A) Update the issue log and refer to the resource management plan to address the situation.
upvoted 0 times
...
Lilli
9 days ago
D) Ask the sponsor for an experienced team member in the company to help the project team.
upvoted 0 times
...
...
Belen
1 months ago
I agree with Vivan. It's important to address the situation according to the plan.
upvoted 0 times
...
Felicitas
1 months ago
Option C is the way to go. Reducing scope is the best approach when you lose a team member. Stakeholders need to be informed, and the project can be adjusted accordingly.
upvoted 0 times
Malcom
4 days ago
A) Update the issue log and refer to the resource management plan to address the situation.
upvoted 0 times
...
Chauncey
8 days ago
D) Ask the sponsor for an experienced team member in the company to help the project team.
upvoted 0 times
...
Glendora
10 days ago
C) Reduce the scope of the project and inform stakeholders.
upvoted 0 times
...
...
Vivan
1 months ago
I think the project manager should update the issue log and refer to the resource management plan.
upvoted 0 times
...

Save Cancel