A team shared a complaint regarding the scrum master during the last sprint review. The team expressed that they were delayed because the
scrum master did not remove impediments, such as scheduling some meetings with external teams and obtaining a room to work collaboratively, among other critical blockers.
What should the project manager do?
Thea
21 days agoJospeh
3 days agoOzell
7 days agoGabriele
9 days agoDaren
24 days agoCristal
3 days agoMajor
10 days agoShonda
1 months agoLizette
1 months agoGolda
3 days agoRickie
5 days agoPeggie
6 days agoErick
23 days agoMozell
26 days agoJamie
1 months agoRaul
2 months agoLeeann
2 months agoRosalind
2 months agoHelene
20 days agoAlishia
23 days agoAdelle
1 months agoBreana
1 months agoNorah
1 months agoWilletta
1 months agoDorothy
2 months ago