Examine the figure given below.
In this project network diagram, what is the total float for Activity I?
The float for Activity I is three days. The early start for Activity I is Day 17 and the late start for
Activity I is Day 20. Therefore, the difference of
the early start and the late start reveals the float as three days. It is possible, and acceptable, to use
the difference of the early finish and the late finish to find the float, as the value will be the same
amount. Answer options B, D, and C are incorrect. These are not the valid calculation for the total
float.
Danica
18 days agoAlease
10 days agoEarnestine
12 days agoCecil
13 days agoLeontine
1 months agoErick
8 days agoJoana
10 days agoLizette
29 days agoYun
1 months agoTheodora
2 months agoAbel
15 days agoMartin
21 days agoReena
27 days agoSilva
1 months agoFreida
2 months agoAlyce
2 months ago