PMI Exam PMI-SP Topic 9 Question 92 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 92
Topic #: 9
[All PMI-SP Questions]

Examine the figure given below.

In this project network diagram, what is the total float for Activity I?

Show Suggested Answer Hide Answer
Suggested Answer: A

The float for Activity I is three days. The early start for Activity I is Day 17 and the late start for

Activity I is Day 20. Therefore, the difference of

the early start and the late start reveals the float as three days. It is possible, and acceptable, to use

the difference of the early finish and the late finish to find the float, as the value will be the same

amount. Answer options B, D, and C are incorrect. These are not the valid calculation for the total

float.


Contribute your Thoughts:

Danica
18 days ago
Five? Really? That seems way too high. I'm going with B - zero. After all, this is a project management exam, not a guessing game. *chuckles*
upvoted 0 times
Alease
10 days ago
I agree with you, I also think it's one.
upvoted 0 times
...
Earnestine
12 days ago
I'm pretty sure it's one, not five.
upvoted 0 times
...
Cecil
13 days ago
I think the total float for Activity I is actually three.
upvoted 0 times
...
...
Leontine
1 months ago
Hmm, I'm not too sure about this one. Let me double-check the calculations. Ah, I got it! The total float for Activity I is one. Easy peasy!
upvoted 0 times
Erick
8 days ago
Oh, okay. Thanks for clarifying!
upvoted 0 times
...
Joana
10 days ago
I double-checked, it's definitely one.
upvoted 0 times
...
Lizette
29 days ago
Are you sure? I calculated it to be three.
upvoted 0 times
...
Yun
1 months ago
I think the total float for Activity I is one.
upvoted 0 times
...
...
Theodora
2 months ago
The network diagram looks a bit confusing, but I think the total float for Activity I is zero. I'm pretty sure that's the correct answer.
upvoted 0 times
Abel
15 days ago
I'm positive it's zero. That's the correct answer.
upvoted 0 times
...
Martin
21 days ago
Are you sure? I calculated it as five.
upvoted 0 times
...
Reena
27 days ago
I believe it is actually three.
upvoted 0 times
...
Silva
1 months ago
I think the total float for Activity I is zero.
upvoted 0 times
...
...
Freida
2 months ago
I believe it is Three because there seems to be some flexibility in the schedule.
upvoted 0 times
...
Alyce
2 months ago
I think the total float for Activity I is Zero.
upvoted 0 times
...