BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 9 Question 92 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 92
Topic #: 9
[All PMI-SP Questions]

Examine the figure given below.

In this project network diagram, what is the total float for Activity I?

Show Suggested Answer Hide Answer
Suggested Answer: A

The float for Activity I is three days. The early start for Activity I is Day 17 and the late start for

Activity I is Day 20. Therefore, the difference of

the early start and the late start reveals the float as three days. It is possible, and acceptable, to use

the difference of the early finish and the late finish to find the float, as the value will be the same

amount. Answer options B, D, and C are incorrect. These are not the valid calculation for the total

float.


Contribute your Thoughts:

Leontine
14 days ago
Hmm, I'm not too sure about this one. Let me double-check the calculations. Ah, I got it! The total float for Activity I is one. Easy peasy!
upvoted 0 times
Yun
4 days ago
I think the total float for Activity I is one.
upvoted 0 times
...
...
Theodora
17 days ago
The network diagram looks a bit confusing, but I think the total float for Activity I is zero. I'm pretty sure that's the correct answer.
upvoted 0 times
Silva
9 days ago
I think the total float for Activity I is zero.
upvoted 0 times
...
...
Freida
18 days ago
I believe it is Three because there seems to be some flexibility in the schedule.
upvoted 0 times
...
Alyce
28 days ago
I think the total float for Activity I is Zero.
upvoted 0 times
...

Save Cancel