Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 9 Question 86 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 86
Topic #: 9
[All PMI-SP Questions]

Examine the figure given below:

If Activity B takes eight days to complete instead of five days as schedule, how long can you now delay Activity H?

Show Suggested Answer Hide Answer
Suggested Answer: A

An activity is an individual element of work that is logically linked to other activities to

form the schedule. Its primary characteristics include an overall duration based upon the resources

applied to it (manpower, material, and equipment), as well as a start and

completion date that is tied to a work calendar. It also has a relationship with other activities

(predecessors and successors).


Contribute your Thoughts:

Lina
1 days ago
I think the answer is A) Three days.
upvoted 0 times
...

Save Cancel