Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 9 Question 43 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 43
Topic #: 9
[All PMI-SP Questions]

Gary is the project manager of the NGH project for his organization. He and the project team have

created the initial WBS. Before Gary and the project team begin creating the activity list, Gary wants

the project team to help him create a unique numbering system for the deliverables identified in the

WBS. What numbering system can Gary and the project team apply to the WBS to identify the

components of the WBS?

Show Suggested Answer Hide Answer
Suggested Answer: A

The code of accounts is a hierarchical numbering system that uniquely identifies each

deliverable of the WBS and segments the WBS by levels

of numbering.

Answer option C is incorrect. Component numbering is not a valid term for project management.

Answer option B is incorrect. A chart of accounts is a financial tracking and assignment tool for

common deliverables and activities an

organization performs for its customers.

Answer option D is incorrect. Activity linkage sequencing is not a valid project management term.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel