Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 9 Question 41 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 41
Topic #: 9
[All PMI-SP Questions]

Della works as a project manager for BlueWell Inc. She has asked her assistant Beth to provide

activity duration estimate for an activity. Beth provides Della the following estimate chart:

What will be the activity duration according to the PERT three-point analysis?

Show Suggested Answer Hide Answer
Suggested Answer: C

A three-point estimate records the optimistic, most likely, and the pessimistic duration

and then records an average for the predicted duration.

Three-point estimate is a way to enhance the accuracy of activity duration estimates. This concept is

originated with the Program Evaluation

and Review Technique (PERT). PERT charts the following three estimates:

Most likely (TM): The duration of activity based on realistic factors such as resources assigned,

interruptions, etc.

Optimistic (TO): The activity duration based on the best-case scenario

Pessimistic (TP): The activity duration based on the worst-case scenario

The expected (TE) activity duration is a weighted average of these three estimates:

TE = (TO + 4TM + TP) / 6

Duration estimates based on the above equations (sometimes simple average of the three estimates

is also used) provide more accuracy.

Here it is,

TE = ( 24 + 28*4 + 36) / 6

= 272/6

= 29 (approx)

Answer options B, D, and A are incorrect. These are not the valid answers for this question.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel