BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 9 Question 29 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 29
Topic #: 9
[All PMI-SP Questions]

You are the project manager of the GHY Project. This project is scheduled to last for one year and

has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are up

posed to be at your second milestone which accounts for half of the project completion. There have

been some errors in the project which has caused you to spend $2,073,654. What is this project's

schedule variance?

Show Suggested Answer Hide Answer
Suggested Answer: C

The schedule variance can be found by subtracting the planned value from the earned

value. In this instance, it is $2,025,000 minus

$2,250,000.

Schedule variance (SV) is a measure of schedule performance on a project. The variance notifies that

the schedule is ahead or behind what

was planned for this period in time. The schedule variance is calculated based on the following

formula:

SV = Earned Value (EV) - Planned Value (PV)

If the resulting schedule is negative, it indicates that the project is behind schedule. A value greater

than 0 shows that the project is ahead of

the planned schedule. A value of 0 indicates that the project is right on target.

Answer option B is incorrect. This is the cost variance for the project.

Answer option A is incorrect. 10 percent is not a valid answer.

Answer option D is incorrect. This is not a valid variance for this question; variances are typically

negative numbers.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel