BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 9 Question 2 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 2
Topic #: 9
[All PMI-SP Questions]

You are the project manager of the NHA Project. This project is expected to last one year with quarterly milestones throughout the year. Your project is supposed to be at the third milestone today but you're likely only 60 percent complete. Your project has a BAC of $745,000 and you've spent $440,000 of the budget-to-date. What is your schedule performance index for this project?

Show Suggested Answer Hide Answer
Suggested Answer: D

The schedule performance index can be found by dividing the earned value by the planned value. In this project, it's $447,000 divided by the $558,750 for a value of 0.80. Schedule performance index (SPI) is the measure of schedule efficiency on a project. It is used in trend analysis to predict future performance. SPI is the ratio of earned value to planned value. The SPI is calculated based on the following formula:

SPI = Earned Value (EV) / Planned Value (PV)

If the SPI value is greater than 1, it indicates better than expected performance, whereas if the value is less than 1, it shows poor performance. The SPI value of 1 indicates that the project is right on target.

Answer option A is incorrect. "80" is not the same value as ".80". Answer option B is incorrect. 1.02 is the cost performance index. Answer option C is incorrect. 102 is not a valid calculation for this question.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel