Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 8 Question 87 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 87
Topic #: 8
[All PMI-SP Questions]

You are the project manager of the NHQ Project. Management has told you that resource leveling will be enforced on your project, but they still want you to complete the project by July 2. With the current resources you have and the resource leveling imposed, you would not be able to finish by the constraint. What document should you update to address this situation?

Show Suggested Answer Hide Answer
Suggested Answer: A

The activity resource requirements will need to be addressed because the imposed

constraint will cause a need for more resource to complete

the activities by July 2.

What is resource leveling heuristics?

Resource leveling heuristics is a prioritization method that allocates inadequate resources to critical

path activities first. It is

a schedule network analysis technique useful to a schedule that has already been analyzed by the

critical path method. It

is used when shared or critical essential resources are only available at certain times, in limited

quantities, or to keep

resource usage at a constant level. It is a technique that resolves resource conflicts by delaying tasks

within their slack

allowances. Resource leveling is the process in which project teams come across problems when

developing their project

schedules. If a company has multiple projects running simultaneously that require the same

resources, then problems can

arise. It can often cause the critical path method to change.

Answer option C is incorrect. The project scope does not need to be addressed as there has not been

a request to reduce or increase the

project scope.

Answer option B is incorrect. The project charter will not change. In fact, the charter will rarely, if

ever, change once has been approved and

signed.

Answer option D is incorrect. The schedule management plan would not be the biggest concern in

this instance. The plan defines how the

schedule will be created, executed, monitored and controlled.


Contribute your Thoughts:

Christiane
2 months ago
Hmm, this is tricky. But I'd say B is the best choice. Updating the schedule management plan seems like the logical way to handle this situation.
upvoted 0 times
Abel
1 months ago
D) Project charter
upvoted 0 times
...
Angelica
2 months ago
C) Project scope
upvoted 0 times
...
Queenie
2 months ago
B) Project schedule management plan
upvoted 0 times
...
Lisha
2 months ago
A) Project activity resource requirements
upvoted 0 times
...
...
Marylou
3 months ago
I'm going with B as well. The schedule management plan is where we document the approach to managing resources and the project schedule.
upvoted 0 times
...
Hildegarde
3 months ago
Definitely B. The schedule management plan is the place to address resource constraints and their impact on the project timeline.
upvoted 0 times
Emilio
1 months ago
Updating the schedule management plan is crucial in this situation. It will help you navigate the resource constraints and still meet the project deadline.
upvoted 0 times
...
Lai
1 months ago
Yes, B is the best option. It will help you manage the project timeline effectively.
upvoted 0 times
...
Jeanice
1 months ago
I agree, B is the correct answer. It's important to update the schedule management plan to address resource constraints.
upvoted 0 times
...
Linn
1 months ago
D) Project charter
upvoted 0 times
...
Terina
1 months ago
C) Project scope
upvoted 0 times
...
Lashanda
1 months ago
B) Project schedule management plan
upvoted 0 times
...
Charlesetta
2 months ago
A) Project activity resource requirements
upvoted 0 times
...
Corrie
2 months ago
No, we should focus on the schedule management plan to address the resource leveling.
upvoted 0 times
...
Ahmad
2 months ago
Should we also consider updating the project activity resource requirements?
upvoted 0 times
...
Jillian
2 months ago
That's right, the schedule management plan is where we address resource constraints.
upvoted 0 times
...
Darci
3 months ago
We should update the project schedule management plan.
upvoted 0 times
...
...
Jamie
3 months ago
But shouldn't we also update the Project activity resource requirements to accurately reflect the resources needed for each activity?
upvoted 0 times
...
Noah
3 months ago
I think the correct answer is B) Project schedule management plan. Resource leveling will impact the project schedule, so we need to update that document.
upvoted 0 times
Jacquelyne
2 months ago
Yes, that document will help us outline how we will adjust the schedule to accommodate the resource constraints.
upvoted 0 times
...
Pedro
2 months ago
I agree, we definitely need to update the project schedule management plan to address the resource leveling.
upvoted 0 times
...
...
Tanja
3 months ago
I think we should update the Project schedule management plan.
upvoted 0 times
...
Beata
3 months ago
I agree with Tanja. The schedule management plan needs to be adjusted to reflect the resource leveling constraints.
upvoted 0 times
...

Save Cancel