Steve is the project manager for the POK Project. He is working with the project customers to determine how frequently they'd like to receive the project information. The customers would like weekly status reports on how the project is performing. Where should Steve document this information?
The float for Activity I is three days. The early start for Activity I is Day 17 and the late start for
Activity I is Day 20. Therefore, the difference of
the early start and the late start reveals the float as three days. It is possible, and acceptable, to use
the difference of the early finish and the late finish to find the float, as the value will be the same
amount. Answer options B, D, and C are incorrect. These are not the valid calculation for the total
float.
Currently there are no comments in this discussion, be the first to comment!