You are the project manager for your organization. You are coaching Allen, a junior project manager,
on how the details of the project's critical path are calculated. Examine the figure given below:
What is the critical path of this project?
The project's Communications Management Plan defines what information will be distributed, when
it will be distributed, to whom it will be
distributed, and the modality of the information.
Answer option D is incorrect. The Schedule Management Plan defines the project work, when the
project work will happen, resource
utilization, and how the schedule will be monitored and controlled.
Answer option C is incorrect. There is a stakeholder management strategy, but not a Stakeholder
Management Plan.
Answer option A is incorrect. The project's Scope Management Plan defines how the scope will be
created, how the changes will be allowed,
how the scope will be executed, monitored and controlled, and finally closed.
Carmelina
2 months agoTori
3 days agoStephane
4 days agoRaymon
1 months agoAnisha
2 months agoAllene
15 days agoDenny
21 days agoDorcas
1 months agoBrandee
2 months agoMike
15 days agoNichelle
16 days agoOsvaldo
17 days agoSueann
2 months agoLelia
2 months agoMajor
2 months agoFranchesca
2 months agoLeota
17 days agoLisbeth
26 days agoJoanna
28 days agoNell
1 months agoXochitl
1 months agoAlfred
1 months agoAmina
2 months agoOdette
2 months agoTyra
2 months agoGlen
3 months agoJeannine
3 months agoFlorinda
3 months ago