BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 8 Question 48 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 48
Topic #: 8
[All PMI-SP Questions]

You are the project manager for your organization. You are working through the control schedule

process. According to the PMBOK, there are four inputs to this process. Which one of the following is

NOT an input to the control schedule process?

Show Suggested Answer Hide Answer
Suggested Answer: A

Schedule data is not an input to the control schedule process. Organizational process

assets are the final input to the control schedule process.

The inputs of schedule control process are as follows:

Project Management Plan

Project Schedule

Work Performance Integration

Organizational Process Assets

Answer option C is incorrect. The project management plan is an input to the control schedule

process.Answer option D is incorrect. The project schedule is an input to the control schedule

process.

Answer option B is incorrect. Work performance information is an input to the control schedule

process.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel