You are the project manager for your organization. You are working through the control schedule
process. According to the PMBOK, there are four inputs to this process. Which one of the following is
NOT an input to the control schedule process?
Schedule data is not an input to the control schedule process. Organizational process
assets are the final input to the control schedule process.
The inputs of schedule control process are as follows:
Project Management Plan
Project Schedule
Work Performance Integration
Organizational Process Assets
Answer option C is incorrect. The project management plan is an input to the control schedule
process.Answer option D is incorrect. The project schedule is an input to the control schedule
process.
Answer option B is incorrect. Work performance information is an input to the control schedule
process.