BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 8 Question 30 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 30
Topic #: 8
[All PMI-SP Questions]

You are the project manager for your organization. You have recently noted some risks associated

with some of the activities in your project. These risks can have schedule and costs impacts on your

project and you need to address the risks through qualitative and quantitative analysis to confirm

the depth of possible impact. Where should you document the risk information concerning the

activities in your project schedule?

Show Suggested Answer Hide Answer
Suggested Answer: C

The project risks are documented in the risk register - including the probability and

impact information. The risk register is an output of the

Identify Risks process.

Risk register is a document that contains the results of the qualitative risk analysis, quantitative risk

analysis, and risk response planning.

Description, category, cause, probability of occurring, impact on objectives, proposed responses,

owner, and the current status of all identified

risks are put in the risk register.

Answer option A is incorrect. The risk management plan addresses that how risks will be identified,

monitored, and controlled.

Answer option D is incorrect. The activity attributes information is needed, but risks are not part of

the activity attributes.

Answer option B is incorrect. The schedule management plan addresses how the schedule will be

created, executed, and controlled.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel